Ohio State University Extension Bulletin

BMPs for Erosion Control for Logging Practices in Ohio

Bulletin 196


Stream Crossings

Figure 21. Culvert stream crossings: culvert slope.



Table 2. Culvert sizing chart.

Recommended Diameters of CulvertsBased on Drainage Area
Pipe DiameterArea Above Pipe
(inches)(acres)

122
154
187
2112
2416
3027
3647
4264
4890
54120
60160
66205
72250
78350

General Guidelines

  1. Avoid stream crossing when possible.
  2. There is one best place to cross a stream.
  3. Cross streams as far up the watershed as possible.
  4. A well-defined channel is a desirable place to cross.
  5. Minimize the amount of road that would impact the Streamside Management Zone (SMZ).
  6. Use portable bridges when practical.
  7. Stream crossings are critical areas that should be restored.

Stream Crossing Design Goals

  1. Cross streams at a right angle (90°).
  2. Break grade as soon as possible on both approaches*.
  3. Armor the stream bottom, and protect the banks from collapsing.

Haul Road Crossings

  1. Use a portable bridge when practical (Figure 22A and 22B).
  2. Use a culvert if necessary (See Table 2).
  3. Gravel should be used to cover temporary culvert placement when necessary; gravel and/or soil is acceptable for permanent installation (Figure 11).
  4. When fording a stream, armor both banks and approaches through break in grade or water diversion device*. Armor the stream bottom with gravel unless a solid rock bottom exists. Geo-Textile fabrics and Geo-Cell should be considered for permanent crossings.

Skid Road Crossings

  1. Use a portable bridge when practical.
  2. Use a culvert or pipe if necessary (see Table 2).
  3. Pole wood crossings should utilize long poles with a 6-inch diameter small end to fill channel level with banks; culverts may need to be installed under the wood to facilitate water flow. Not recommended for perennial streams.
  4. Utilize standing bumper-trees on both banks when possible to keep wood and logs behind the skidder.
  5. Approaches should be stabilized up through the break in grade or water diversion device* to minimize rutting and collapsing of the banks.
When crossing low wet areas where no channeled water flow exists, use tree tops, brush, mudmats, etc., to armor the area. Break grade on both sides and daylight if possible.

Stream Crossing Restoration

  1. All stream crossings should be restored.
  2. Remove bridge, culvert, soil, and all wood from temporary crossings.
  3. Carefully restore stream bottom and banks to original contour where necessary.
  4. Water bar or maintain break in grade or water diversion device.*
  5. Grade roads to minimize rutting.
  6. Seed, fertilize, lime, and mulch all disturbed soil up through break in grade or water diversion device.

* Breaks in grade or water diversion devices should be installed with sufficient filter strip below them to keep sediment from being transported to the stream.

Bridges

General Guidelines




Figure 22A. Portable logging bridge installed with skidder.

Figure 22B. Alternative bridge design.

Figure 23A. Pole crossing.

Figure 23B. Pole crossing.

Back | Forward | Table of Contents