Mound System Design Example

Step 10. Determine Mound Sand Fill Downslope Depth.

The bottom of the distribution area must be constructed level. Therefore, the sand fill will be deeper on the downslope side of the distribution area.

Mound Sand Fill Downslope Depth = (Mound Sand Fill Upslope Depth) + (Site Slope)*(Distribution Width)

Mound Sand Fill Downslope Depth

Mound Sand Fill Downslope Depth:

The site slope is 12% in this design example.

Mound Sand Fill Downslope Depth = (Mound Sand Fill Upslope Depth) + (Site Slope)*(Distribution Width)
= (22 inches) + (0.12)*(48 inches)
= 28 inches